Worksop Open Market – Relocation and improved operation Project Value – £140,000 Delivery Date – April 2011 Bassetlaw District Council needed to relocate Worksop’s fixed-stall Open Market to free up the site for a key use in its town centre...
by hbadmin | Jun 7, 2023 | Case Studies
Blackburn – Design and Fit-out of new build Market Hall Project Value – £8.5million Delivery Date – June 2011 This project required the replacement of Blackburn’s crumbling 1960’s Market Hall which housed 120 Tenants. Appraisal confirmed the most...
by hbadmin | Jun 7, 2023 | Case Studies
Woking Market Relocation and Modernisation Project Value – £5 million Delivery Date – July 2015 In 2013 Woking Council opted to relocate it’s Open Market to enable the next phase of their Town Centre regeneration plans. Relocating the Market was a...
by hbadmin | Jun 7, 2023 | Case Studies
The Darlington Markets Partnership Project Value – £3.5 million Delivery Date – Ongoing in 2017 Darlington Borough Council entered into a 99-year partnership with the private sector and staff were transferred by TUPE. The Operator assumed responsibility...
by hbadmin | Jun 7, 2023 | Case Studies
Limerick, Eire – Design Consultancy and Business plan The Market Commissioners needed to develop a design and business plan to revitalise Limerick’s ‘Saturday-only’ Open Market standing in a Courtyard between semi-derelict historic buildings and used during the...
by hbadmin | Jun 2, 2023 | Case Studies
Accrington Market Hall: Refurbishment and Enterprise Haven Project Value – £2.2million Delivery Date – June 2010 Remodelling and long-overdue building repairs were needed for this historic Grade 2-listed Market Hall. The project was funded by owners,...